The Town has partnered with Thomas and Hutton to perform a multi-year comprehensive stormwater system evaluation of the Old Village. The study area wasEx 14 - Construction Sequence Exhibit Opens in new window broken into 27 drainage basins or areas of land that drain to a common point. The level of service for each basin was determined by comparing system capacity to projected peak runoff during a storm.

The Edwards Park Basin was ranked second out of 27 basins and makes up a 138 acre area serving 434 parcels. The proposed system will provide a ten-year storm level of service. However, many homeowners will still see ponding during heavy rain events and flooding could occur if the 10-year design storm is exceeded. The biggest change will be how quickly the water level recedes. Also, areas that previously relied solely on infiltration will now be connected to the new drainage system. Our goal is to limit flooding impacts to structures. Ponding in yards is anticipated during more intense storms. 

The original drainage systems incorporated shallow roadside swales. Over time, many of these swales have filled in. In many cases, homeowners added street parking in these areas. As part of this project, many of the swales will be restored within the right-of-way. Homeowners should maintain these areas to help their lots drain and also to help their upstream neighbors' lots drain. 

The construction will include installing new pipes, upsizing old pipes, and re-establishment of swales. Replace with, the town has averted the removal of any large trees in the design.   Impacts to root systems will be carefully evaluated and monitored by an Arborist to ensure every effort is made to protect the health and lifespan of all trees near the project site. To see a map of the project area, please click this link:

Status (As of September 25, 2023)

  • Design is nearing completion

Schedule

  • Permits to be updated December 2023

    Bid Advertisement to be Early 2024
    Notice to Proceed March 2024
    In operation by May 2025

Cost

$10.8M

Resources

View the Old Village Watershed Study
View Existing Drainage - Existing Land Use - 100yr Max Flood Depth
View Construction Sequence Exhibit