Shem Creek Phase III

sc phase iii

Description

This project is part of the Coleman Boulevard Revitalization Project. This is a continuation of Shem Creek Park. The project is an independent pedestrian bridge that will span the creek making a connection with the Coleman Blvd sidewalk on the east side and the existing boardwalk on the west side. This project is consistent with the Comprehensive Plan in that it increases public access to the water, enhances sense of place, increases connectivity, and prioritizes the pedestrian environment.

Status

Phase III Update: The final design for the next phase to provide a pedestrian overpass is complete. The Town’s Committee awarded the project to Cape Romain Contractors, with the condition of securing all permits. The Federal Critical Area Permit is under review by the Coast Guard and is anticipated to be released in November 2018.

Schedule

  • Conceptual Design/ Planning: November 2016
  • Permitting: September 2017
  • Design: January 2018
  • Bidding/Construction: Completed by June 2018

Cost

$3,061,000 (Funding date started 7/1/2015; Fully funded by the Hospitality Recreation, Hospitality Transportation, and TIF Revenue)

Resources

Phase 3 Project Overview

Current View

View of Creek Rendering

Rendering Shem Creek Park 

Contact

Kevin Mitchell, Project Manager