Shem Creek Bridge Bike Lanes

SHEM CREEK
Shem Creek Bike Lane Project Page Banner_1350x367

Description

This project will add 4'-5’ marked bike lanes on Coleman Boulevard across the Shem Creek Bridge between Pelzer Drive and Mill Street. This will enable over 1.5 miles of continuous bike lanes on Coleman Boulevard from Houston Northcutt Boulevard to Pherigo Street.

Status

A public information meeting was conducted and SCDOT has approved the design exception. Preliminary plans have been submitted to SCDOT and are currently under their review.

Schedule

  • Complete Design:  Complete
  • Begin Construction: July 2023
  • Complete Construction: October 2023

Cost Estimate

  • $891,000 

Resources

Shem Creek Bike Lane Project Area

Shem Creek Bike Lane Form (11/6/17)

Contact

James Aton, Project Manager