Patriots Point Gateway Intersection Improvements

Gateway
Patriots Point Project Page Banner_1350x367

Description

The scope of this proposed project will construct intersection improvements by adding turn lanes on Coleman Boulevard, Magrath Darby Boulevard and Patriots Point Road.

Status

The project has been awarded with a notice to proceed set for February 15, 2022. The project is currently in a 7 month utility relocation window with roadway construction expected to being in September 2022. 

Schedule

  • Design:  Complete
  • Begin Construction:  February 2022
  • Complete Construction: August 2023

 Project Cost Estimate

$9,672,785